    Construcción de los drenajes y terrapplenes de la careterra Costanera Sur, ruta nacional N° 34 sección: Quepos-Savegre-Barú. Licitación pública internaciobnal N° LI-002-2005

    Thumbnail
    View/Open
    LM-AT-99-08 Construcción de Drenajes y terraplenes de la carretera Costnera Sur RN N°34 Sección; Quepos-Savegre-Barú.pdf (602.8Kb)
    Date
    2008-10
    Author
    Chaverri Jiménez, Jenny
    Salas Chaves, Mauricio
    Acosta Hernández, Erick
    Metadata
    Show full item record
    Abstract
    El proyecto aún mantiene sin atender algunos de los hallazgos y observaciones contemplados en los informes de Auditoria Técnica Externa LM- AT-25-2007 con fecha de noviembre del 2007 y LM-AT-15-2008 de mayo de 2008. El derecho de vía del proyecto aún no está totalmente expropiado, razón que origina algunas de las reducciones importantes en el ancho de la vía, que por falta de señalización vial apropiada, crean puntos de riesgo para los usuarios de la vía, y eventuales atrasos en la construcción de la vía. Es importante realizar una adecuada inspección de los métodos constructivos y del acabado que se le da a ciertas obras para detectar posibles inconsistencias y que por su ubicación dentro del proyecto o función dentro de proyecto, luego son difíciles de solventar.
     
    The project still does not address some of the findings and observations contemplated in the reports of External Technical Audit LM-AT-25-2007 dated November 2007 and LM-AT-15-2008 May 2008. The right-of-way of the project is not yet fully expropriated, which is the reason for some of the significant reductions in the width of the road, which due to the lack of appropriate road signs, create risk points for the users of the road, and eventual delays in the construction of the road. It is important to make an adequate inspection of the construction methods and the finishing that is given to certain works to detect possible inconsistencies and that due to their location within the project or function within the project, they are difficult to solve.
     
    URI
    https://www.lanamme.ucr.ac.cr/repositorio/handle/50625112500/1160
    Collections
    • Informes [1094]

     © 2018-2020  Laboratorio Nacional de Materiales y Modelos Estructurales
    Contact Us | Send Feedback | 📞 +506 2511-2500 |  ✉ direccion.lanamme@ucr.ac.cr

     

     

    Browse

    All of DSpaceCommunities & CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

    My Account

    LoginRegister

     © 2018-2020  Laboratorio Nacional de Materiales y Modelos Estructurales
    Contact Us | Send Feedback | 📞 +506 2511-2500 |  ✉ direccion.lanamme@ucr.ac.cr