    Mejoamiento de la ruta N° 21, Santa Rita-Jicarallepanto-Playa Naranjo II, Sección Pavones, sin interseeción Corozal LPCO-019-99

    Thumbnail
    Ver/
    LM-PI-PV-AT-37-04 Mejoramiento de la Ruta N°21 Santa Rita - Jicaral-Lepanto-Playa Naranjo II. Sección Pavones.pdf (483.5Kb)
    Fecha
    2004
    Autor
    Rodríguez Mora, Marcos
    Arriola Guzmán, Raquel
    Herrera Jiménez, Edgar
    Metadatos
    Mostrar el registro completo del ítem
    Resumen
    De la presente auditoría se tiene la siguiente información, de algunos de los problemas encontrados a lo largo del documento: Se da una falta de concordancia entre lo ejecutado y lo establecido en las especificaciones especiales, diseños y planos constructivos. Se realizaron cambios con respecto a lo establecido en los planos, sin que exista evidencia de una orden de modificación emitida por el ingeniero de proyecto en la que se justifiquen dichos cambios. Además, los programas de trabajo no fueron utilizados como base para el control de avance de las obras ni para el pago de reajustes, debido a que no se realizaron las correspondientes actualizaciones de estos programas, sin embargo, se otorgaron pagos sin cumplir con este requisito del contrato.
     
    From the present audit it has the following information, of some of the problems found throughout the document: There is a lack of agreement between what was executed and what was established in the special specifications, designs and construction plans. Changes were made with respect to what is established in the plans, without evidence of a modification order issued by the project engineer in which such changes are justified. In addition, the work programs were not used as a basis for the progress control of the works or for the payment of readjustments, due to the fact that the corresponding updates of these programs were not made, however, payments were granted without complying with this requirement. of the contract.
     
    URI
    https://www.lanamme.ucr.ac.cr/repositorio/handle/50625112500/1073
    Colecciones
    • Informes [1088]

     © 2018-2020  Laboratorio Nacional de Materiales y Modelos Estructurales
    Contacto | Sugerencias | 📞 +506 2511-2500 |  ✉ direccion.lanamme@ucr.ac.cr

     

     

    Listar

    Todo DSpaceComunidades & ColeccionesPor fecha de publicaciónAutoresTítulosMateriasEsta colecciónPor fecha de publicaciónAutoresTítulosMaterias

    Mi cuenta

    AccederRegistro

     © 2018-2020  Laboratorio Nacional de Materiales y Modelos Estructurales
    Contacto | Sugerencias | 📞 +506 2511-2500 |  ✉ direccion.lanamme@ucr.ac.cr